Public-Private Partnership in India: Models, VGF, HAM, Kelkar Committee and Monetisation for RBI Grade B Finance

Last updated: 2026-11-13 · MockMentor

"Public-Private Partnership" ends the syllabus line on alternate sources of finance in the General Topics unit of the RBI Grade B Phase 2 Finance syllabus. It is a favourite of descriptive papers because it brings together infrastructure, public finance and risk sharing. Questions ask about PPP models such as BOT, DBFOT and the Hybrid Annuity Model, the Viability Gap Funding scheme, the Vijay Kelkar Committee and the National Monetisation Pipeline. This chapter covers all of these, with the lessons from India's PPP experience.

In one line: a PPP is a long-term contract in which a private partner finances, builds or runs a public asset or service and shares its risks and rewards with the government; India uses it widely in roads, airports, ports and power, with support from Viability Gap Funding and newer models such as HAM and asset monetisation.

Basic concepts

  • Public-Private Partnership (PPP): an arrangement between a government or statutory body and a private entity for providing public assets or services, in which investment is made or management is carried out by the private entity for a specified period, with risks shared and payment linked to performance. This follows the definition used by the Ministry of Finance.
  • Concession: the right given by the government to a private party to build or run an asset and collect user charges, for a fixed period.
  • Concessionaire: the private party that holds the concession, usually through a special purpose vehicle (SPV).
  • Annuity: fixed periodic payments by the government to the private partner, regardless of traffic or demand.
  • Viability gap: the shortfall between the cost of a project and what it can earn, which makes it unattractive to private investors without support.
  • Value for money: the test of whether a PPP gives better results for the public than a project carried out by the government itself.

Why in News?

  1. The Union Budget 2025-26 announced a second National Monetisation Pipeline for 2025 to 2030, with a target of ₹10 lakh crore of fresh capital from monetising public assets, building on the first pipeline of 2021 to 2025.
  2. The same Budget asked infrastructure ministries to prepare a three-year pipeline of projects that can be taken up in PPP mode, and allowed states to seek support from the India Infrastructure Project Development Fund.
  3. The Union Budget 2026-27 raised capital expenditure for infrastructure to ₹12.2 lakh crore, which increases the need for private participation in projects.
  4. The Hybrid Annuity Model remains the main PPP model for national highways, after the BOT toll model saw few takers.

Why PPPs are needed

  1. The government's resources are limited, while infrastructure needs are huge.
  2. Private partners bring efficiency, technology, innovation and management skills.
  3. Risks can be allocated to the party best able to manage them, such as construction risk to the builder.
  4. Life-cycle thinking: when the same party builds and maintains an asset, it has a reason to build well.
  5. Projects can be completed faster with performance-linked payments.
  6. The government can focus on regulation and planning instead of running assets.

Features of a PPP

  • A long-term contract, often 15 to 30 years or more.
  • The private party usually invests its own capital and raises debt.
  • Payment through user charges (tolls, tariffs), government payments (annuities) or both.
  • Risks and rewards shared according to the contract.
  • The asset usually returns to the government at the end of the concession.
  • Performance standards and penalties written into the contract.

PPP models

The models differ in how much responsibility, risk and ownership pass to the private party.

Model Private role Ownership Example
Service contract Performs a specific service, such as billing or maintenance, for a fee Government Meter reading in a water utility
Management contract Manages operations of an asset for a fee, often with performance incentives Government Running a hospital or a railway station
Lease contract Pays the government to run an asset and keeps user charges; bears operating risk Government Leasing of a port terminal
Concession Finances, builds or upgrades, and runs an asset, collecting user charges for a long period Government (asset reverts) Highway or airport concessions
Build-Operate-Transfer (BOT) Builds, operates and collects charges, then transfers to the government Government at the end BOT toll roads
Build-Own-Operate-Transfer (BOOT) Owns the asset during the concession, then transfers it Private, then government Some power plants
Build-Own-Operate (BOO) Builds, owns and operates for an indefinite period Private Independent power producers
Design-Build (DB) Designs and builds for a fixed price; government operates Government Bridges and buildings
Design-Build-Maintain (DBM) Designs, builds and maintains for a period; government operates Government Roads with maintenance contracts
Design-Build-Operate (DBO) Designs, builds and operates; government finances Government Water treatment plants
Design-Build-Finance-Operate (DBFO) or DBFOT Designs, builds, finances and operates, and then transfers Government at the end Highways, metro lines
Toll-Operate-Transfer (TOT) Pays the government upfront for the right to collect tolls on an existing road for a period Government Monetisation of built highways
Hybrid Annuity Model (HAM) Builds and maintains; government pays part during construction and the rest as annuities Government National highways since 2016

Engineering, Procurement and Construction (EPC) is not a PPP: the government pays the contractor to build and keeps all other risks.

BOT variants for roads

Variant How the private party is paid Who bears traffic risk
BOT (Toll) Collects tolls from users Private party
BOT (Annuity) Receives fixed annuities from the government Government

Hybrid Annuity Model (HAM)

The HAM was introduced by the Ministry of Road Transport and Highways in 2016, after BOT toll projects ran into losses and EPC projects strained the budget.

Feature Detail
Government share 40% of the project cost, paid during construction in instalments linked to milestones
Private share 60%, through equity and debt
Payment The government collects tolls itself and pays the private party the remaining 60% with interest as biannual annuities over 15 years, plus operation and maintenance payments
Risk Traffic and revenue risk with the government; construction and maintenance risk with the private party
Benefit Lower equity needs and lower risk for developers, which revived private interest

Risk allocation in PPPs

Risk Usually borne by
Land acquisition and clearances Government
Design and construction Private party
Operation and maintenance Private party
Demand or traffic risk Private party in toll models; government in annuity models
Financing and interest rate Private party
Change in law and policy Government
Force majeure (natural disasters, war) Shared
Inflation Often shared, through indexation of tolls or annuities

The principle is that a risk should be borne by the party that can best control or absorb it.

Government support for PPPs in India

Viability Gap Funding (VGF)

The Scheme for Financial Support to PPPs in Infrastructure, known as the VGF scheme, started in 2006 and was revised in 2020.

Feature Detail
Purpose A grant to make economically justified but commercially unviable projects attractive
Eligibility PPP projects in infrastructure sectors, awarded through open competitive bidding to private companies
Support (general) Up to 20% of total project cost from the central government, plus up to 20% from the sponsoring authority
Support (social infrastructure, from 2020) Up to 30% from the centre and 30% from the state or sponsoring authority for sectors such as health, education, water and waste
Release Disbursed during construction after the private party has spent its equity
Administered by Department of Economic Affairs, Ministry of Finance, with an Empowered Committee and Institution

Other institutional support

Institution or tool Role
Public Private Partnership Appraisal Committee (PPPAC), 2005 Appraises central PPP projects above a cost threshold
India Infrastructure Project Development Fund (IIPDF), 2007 Funds the cost of preparing PPP projects, such as consultants and feasibility studies
India Infrastructure Finance Company Limited (IIFCL), 2006 Long-term loans and credit enhancement for infrastructure
Model Concession Agreements (MCAs) Standard contracts for sectors such as highways, ports and airports, reducing negotiation time
PPP cell in the Department of Economic Affairs and in states Promotion and capacity building
National Infrastructure Pipeline (NIP), 2019 A list of planned projects across sectors
NaBFID, 2021 Development financial institution for infrastructure
InvITs Allow developers to recycle capital by selling completed projects to investors

The Vijay Kelkar Committee (2015)

After many PPP projects ran into disputes and stalled, the government set up the Committee on Revisiting and Revitalising the PPP Model of Infrastructure Development, chaired by Vijay Kelkar. It reported in November 2015. Its main recommendations were:

  1. Amend the Prevention of Corruption Act, 1988, to distinguish genuine errors of judgement from corruption, so that officials are not afraid to take decisions.
  2. Set up an Infrastructure PPP Project Review Committee to evaluate stressed projects and an Infrastructure PPP Adjudication Tribunal to settle disputes quickly.
  3. Set up an independent regulator for sectors where none exists, such as roads and railways.
  4. Avoid PPPs for very small projects, where the cost of contracting outweighs the benefits.
  5. Create a mechanism to renegotiate contracts in a fair and transparent way.
  6. Make the Swiss challenge method (in which an unsolicited proposal is put to open challenge) less common, as it lacks transparency.
  7. Use PPPs only where they give value for money, not just to keep borrowing off the budget.
  8. Build capacity in government and set up an institute for research on PPPs (3PI).

Several recommendations were accepted in part, such as amendments to the Prevention of Corruption Act in 2018 and the creation of the HAM.

Asset monetisation

National Monetisation Pipeline (NMP)

The first NMP, launched in August 2021, estimated a potential of ₹6 lakh crore over 2021-22 to 2024-25 by leasing core assets of the central government to private parties, while ownership stays with the government.

Sector Examples of monetisation
Roads TOT bundles and InvITs of the National Highways Authority of India
Railways Stations, passenger trains, freight corridors, stadiums
Power Transmission lines and hydro, solar and wind assets
Telecom BharatNet fibre and towers of BSNL and MTNL
Ports, airports, warehousing, mining and pipelines Leases and concessions

Monetisation uses models such as TOT, operate-maintain-transfer and InvITs. It is not privatisation, because the asset returns to the government. The second NMP, announced in the Union Budget 2025-26, covers 2025 to 2030.

Advantages of PPPs

  1. Brings private money and reduces the burden on public budgets.
  2. Faster completion and better quality through performance-linked payments.
  3. Efficient operation and maintenance.
  4. Innovation in design and technology.
  5. Risk sharing with experienced private partners.
  6. Better service delivery to users.

Challenges in India's PPP experience

  • Aggressive bidding: developers bid unrealistic revenue to win contracts, then sought renegotiation.
  • Land acquisition and clearance delays: caused cost overruns and stalled projects.
  • Disputes and slow resolution: arbitration and court cases took years.
  • Stressed balance sheets: many infrastructure firms and their bank lenders faced losses after 2012, contributing to the twin balance sheet problem.
  • Inflexible contracts: no fair way to deal with changes in traffic or costs.
  • Lack of independent regulators: the government is both a party to the contract and the referee.
  • Public opposition to user charges: resistance to tolls and tariffs.
  • Weak capacity in government: to design, appraise and monitor complex contracts.
  • Fiscal risks: contingent liabilities from guarantees and annuities can strain budgets later.

Way forward

  1. Choose PPP only where it gives value for money, using a proper appraisal.
  2. Allocate risks sensibly and complete land acquisition and clearances before bidding.
  3. Set up independent sector regulators and a fast dispute resolution system.
  4. Build a deep market for long-term finance, including infrastructure bonds and InvITs.
  5. Strengthen state and municipal capacity to design and run PPPs.
  6. Record contingent liabilities transparently in budgets.
  7. Extend PPPs to social infrastructure, such as health and education, with VGF support.

International bodies

  • United Nations Economic and Social Commission for Asia and the Pacific (ESCAP): promotes PPPs in the region and has published guidebooks for policymakers.
  • International Project Finance Association (IPFA): a non-profit body that promotes project finance and PPPs worldwide.
  • World Bank Group's Public-Private Infrastructure Advisory Facility (PPIAF) and Global Infrastructure Hub (set up by the G20): support PPP capacity in developing countries.

Possible exam and interview questions

  1. Explain the main PPP models used in India. Why did the Hybrid Annuity Model become popular for highways? (620 words)
  2. What were the key recommendations of the Vijay Kelkar Committee on PPPs? How far have they been implemented? (420 words)
  3. What is Viability Gap Funding, and how was it revised in 2020?
  4. Distinguish between asset monetisation and privatisation.
  5. Interview: Should PPPs be used for hospitals and schools?

Related reading: alternate sources of finance, Union Budget concepts, and development financial institutions.